Offshore Commissioning Merkur Wind Farm

2019-01-15

Merkur is among the top 10 biggest projects offshore worldwide (in 2018) composed by 66 units of the GE Haliade 150 6MW with a total capacity of 396MW. The wind farm is expected to produce 1,750 GWh of electricity a year, enough to power some 500,000 local homes.

Endiprev was involved with the project since the beginning providing skilled engineers to support on engineering documentation, factory assembly, validation and verification works, onshore punch lists and commissioning. More than 60 electrical engineers were involved onsite daily living on the Service Operations Vessel (SOV) on a 14 days’ work and 14 days’ rest rotation scheme.

Endiprev performance on this project was recognized by our customer and our Offshore Team is already working on future projects.
Endiprev, is at this point the only field services provider in the world with offshore track record in 3 continents!